Defense of Contractor - Davis-Bacon Prevailing Wage Claims

This case concerned the construction of a marine boat dock on an island in Boston Harbor. The Plaintiff claimed entitlement to unpaid wages and enhanced wages under the federal prevailing wage statute known as the Davis Bacon Act. The Plaintiff sought treble damages and legal fees.

Under the Davis Bacon Act construction workers on federally funded projects must be paid specified wage rates (classified according to each trade and the locale of the project) for time spent on the job site. In this case the Plaintiff argued he was not paid for time spent on the "site of the work" as defined in the statute. He also took the position that since the work of constructing the dock was performed from a barge, workers should be compensated at the federal Davis Bacon rates while the barge was en route to the island where the boat dock was being constructed, in addition to the time spend there with the barge anchored while it served as the work platform. The travel on the barge each day was about 3 hours for a round trip.

There were contested facts as to whether and when the Plaintiff was actually on the work site. There was a legal issue regarding the definition of the "site of the work" whether the mobile barge was the "site of the work" while in transit to the island. If the Plaintiff prevailed on any of his claims it would have opened the door to claims from other construction workers on this same project to file similar suits.

The case was tried before a Maine Superior Court Justice in June 2013. The Court issued a decision in August 2013 finding in favor of our client on all claims.

Firm Highlights

Publication/Podcast

Is the Coronavirus Pandemic a Force Majeure?

Publication/Podcast

Massachusetts COVID-19 Essential Services as they Relate to the Construction Industry

On March 23, 2020, Governor Baker issued “an emergency order requiring all businesses and organizations that do not provide ‘COVID-19 Essential Services’ to close their physical workplaces and facilities to workers, customers and the...

Matter

Client Recovers on Claim On Differing Site Conditions Claim Involving Subsurface Contaminated Soils

We successfully resolved a substantial claim for our client, a large, Maine based site contractor, stemming from differing site conditions encountered on an aviation facility owned by project federal government. The case stemmed from...

Matter

Project Owner Breached Contract by Attempting to Terminate Contractor

Our client, large construction contractor, completed construction of a new entry at a public building. The scope of work included construction of new concrete sidewalks, stairs, accessibility ramp, canopy, lighting, railings and a non-load...

News

Nearly 80 Verrill Attorneys Recognized by Best Lawyers® 2021, Including a Dozen Named Lawyers of the Year

(August 24, 2020) – Nearly 80 Verrill attorneys were recognized as "Best Lawyers" by Best Lawyers® 2021 , including 12 attorneys named “Lawyer of the Year,” a distinguished recognition for only a single lawyer...

Matter

Breach of AIA Construction Contract and Waiver of Consequential Damages By Owner

Our client, a general contractor, and the project owner signed an American Institute of Architect A101 contract with accompanying A201 general conditions. The project included construction of a new office/retail building, and associated site...

Matter

Engineering Malpractice

We asserted claims on behalf of a large private institution related to defective design and installation of a geothermal heating and cooling system in a high profile public building. The matter was settled favorably...

Matter

Procurement

We have assisted many owners, and contractors in design and construction contracting including: Massachusetts Institute of Technology Investment Management Company on over a billion dollars in projects in Kendall Square area of Cambridge, Massachusetts...

Matter

Defense of Breach of Contract, Negligent Construction and Breach of Duty of Workmanship Claims

We successfully defended a large mechanical contractor in connection with lawsuit stemming from the comprehensive failure of the hydronic piping system in a resort hotel's heating and cooling system. Through fact and expert witness...

Publication/Podcast

City of Portland Releases Guidelines and Procedures for All Construction Sites and Workers at all Public Works

On Monday, March 30, I participated in a video conference on construction activities and COVID-19 sponsored by the Portland Chamber of Commerce with various City of Portland officials and representatives of the developer/contractor community...