Resources
Experience

Defense of Contractor - Davis-Bacon Prevailing Wage Claims

This case concerned the construction of a marine boat dock on an island in Boston Harbor. The Plaintiff claimed entitlement to unpaid wages and enhanced wages under the federal prevailing wage statute known as the Davis Bacon Act. The Plaintiff sought treble damages and legal fees.

Under the Davis Bacon Act construction workers on federally funded projects must be paid specified wage rates (classified according to each trade and the locale of the project) for time spent on the job site. In this case the Plaintiff argued he was not paid for time spent on the "site of the work" as defined in the statute. He also took the position that since the work of constructing the dock was performed from a barge, workers should be compensated at the federal Davis Bacon rates while the barge was en route to the island where the boat dock was being constructed, in addition to the time spend there with the barge anchored while it served as the work platform. The travel on the barge each day was about 3 hours for a round trip.

There were contested facts as to whether and when the Plaintiff was actually on the work site. There was a legal issue regarding the definition of the "site of the work" whether the mobile barge was the "site of the work" while in transit to the island. If the Plaintiff prevailed on any of his claims it would have opened the door to claims from other construction workers on this same project to file similar suits.

The case was tried before a Maine Superior Court Justice in June 2013. The Court issued a decision in August 2013 finding in favor of our client on all claims.

Firm Highlights

Matter

Recovery From Surety and Professional Liability Carrier for Defective Turbine and Biomass Energy Facility Components

Our client developed a biomass fired cogeneration power facility to sell power back to the grid and to support its sawmill operations. As part of this project, it entered into a $13+ million contract...

Matter

Subcontractor Prevails on Wrongful Termination and Delay Claims Following 18 Day Arbitration

Our client was terminated as a mechanical subcontractor on a U.S. Navy project at the Portsmouth Naval Shipyard in Kittery, Maine for alleged delays. Our client and its surety faced claims for costs of...

Publication/Podcast

Say What You Mean, Mean What You Say…Gorelick v. Star Markets: A Study in Indemnity

Indemnity clauses in contracts are a valuable tool for allocating risk among the contracting parties, most often risk attendant to personal injury and property damage, and their effect can be far-reaching. Despite their significance...

Matter

Procurement

We have assisted many owners, and contractors in design and construction contracting including: Massachusetts Institute of Technology Investment Management Company on over a billion dollars in projects in Kendall Square area of Cambridge, Massachusetts...

Matter

Successful Representation of Insurer before U.S. District Court for the District of Maine

Verrill successfully represented an insurer before the U.S. District Court for the District of Maine in an insurance coverage matter alleging that the insurer improperly denied a defense and indemnification to a landlord under...

News

Verrill Welcomes Michael B. Donahue to the Firm’s Construction Group

Matter

Elections and Constitutional Law: Successfully Challenged Certification of Initiative Petition

In a victory for consumers and the ride-hailing public, the Massachusetts Supreme Judicial Court recently barred the Secretary of State from placing on the November ballot initiative petitions proposed by companies such as Uber...

Publication/Podcast

Litigation Update: Jack Daniels V. Bad Spaniels. Is It Parody or Is It Trademark Infringement?

This week the U.S. Supreme Court will hear argument in the case, Jack Daniel’s Properties Inc. v. VIP Products LLC, U.S. Doc. No. 22-148, to decide the question: Can we do that? It’s been...

Contact Verrill at (855) 307 0700