Maine Department of Environmental Protection Issues Draft Wind Energy Act Rules

November 15, 2017 Alerts and Newsletters

After more than a year of pre-rulemaking process including the issuance of two drafts, the Maine DEP has commenced formal rulemaking and today issued draft rules for wind energy developments in Maine. The formal draft largely tracks the most recent pre-rulemaking version issued in January 2017. The draft rules include standards for evaluating scenic impacts, limits on shadow flicker, provisions related to public safety, and requirements for demonstrating significant tangible benefits.

In many respects, the draft rules codify existing DEP practice. There are several significant departures, however, from current practice.

  1. The new provisions on decommissioning do not allow consideration of salvage value when estimating costs and establishing the required decommissioning fund. The decommissioning fund must be fully funded and in place prior to commencement of construction and must be re-evaluated every two years during the life of the project. This change would substantially increase the costs associated with the required decommissioning fund.
  2. The applicant is required to provide evidence of a power purchase agreement or other evidence demonstrating the intended sale of the project's output to a third party. The DEP has not previously required evidence of a power purchase agreement and does not generally evaluate the economics of projects it reviews or require a showing that the output (whether an energy project or non-energy development) will be sold to a third party.
  3. The applicant must provide evidence of the project's effect on electrical rates directly attributable to the project. The impact of any single generation source on electrical rates in Maine is a complex undertaking that requires sophisticated modeling and assumptions about future operation of the electrical grid, future energy mix and prices in the region, and a myriad of other factors. Importantly, in enacting the Wind Energy Act the Legislature made specific findings on the positive effect of wind power on electrical rates and recognized that the environmental review agencies did not have the expertise to evaluate the impact of new generation on electrical rates. As a result, there are no statutory standards related to evaluating the impact of a project on electrical rates.
  4. The safety setbacks from property lines have been increased from the existing standard of 1 ½ times the distance to the tip of the fully extended blade, to 1 ½ times the hub height plus rotor diameter.

The DEP is holding a public hearing on the draft rule on December 6 at 1:00 PM in Augusta, and is accepting public comment on the draft rule through December 18, 2017.

Firm Highlights

Matter

Power Purchase Agreement Approvals

Represented a New York wind developer in proceedings in Connecticut, Massachusetts, and Rhode Island to obtain regulatory approval of power purchase agreements with utilities in those three states pursuant to their tristate clean energy...

Blog

COVID-19 Alert: State of Maine and City of Portland Issue Orders to Close Non-essential Businesses; Utility Services to Continue

On Tuesday March 24, 2020, both the City of Portland and the State of Maine issued comprehensive new limitations on business establishments in order to further limit the spread of the coronavirus. Both actions...

Matter

Permitting

Served as counsel to Novatus Energy LLC on several wind power projects it owns and operates in Maine, including the Bingham Wind Project, which at 186 MW is the largest wind power project in...

Matter

Weaver Wind Project Development

Verrill represented Longroad Energy on development of the Weaver wind project in Maine. Longroad Energy is a Boston, MA-headquartered renewable energy developer focused on the development and operation of wind and solar energy projects...

Blog

COVID-19 Alert: Massachusetts Closes “Non-essential” Businesses; Utility Services to Continue

The response to COVID-19 by states across the U.S. has continued to evolve rapidly. In Massachusetts, due to growing concerns over the spread of coronavirus, Governor Charlie Baker issued a “ shelter in place&rdquo...

Blog

Verrill’s Jim Cohen to Moderate Portland Chamber’s “Eggs & Issues” Discussion with Key State Officials regarding COVID-19

On Wednesday April 8, Verrill attorney and Portland Community Chamber of Commerce president James Cohen will moderate the Portland Chamber’s first-ever “virtual” Eggs & Issues on the subject of Maine’s response to the COVID-19...

Matter

Sale of Wind Projects

Served as outside environmental counsel to SunEdison in connection with wind power projects in Maine. Following SunEdison's voluntary petition for reorganization under Chapter 11 of the Bankruptcy Code, Verrill provided advice and support in...

Blog

Recent Maine Legislation Triggers Amendment to PUC Consumer Protection Rules

Last year, the Maine Legislature enacted three bills requiring amendments to the Public Utilities Commission (PUC) Rules in Ch. 815: Consumer Protection Standards for Electric and Gas Transmission and Distribution (T&D) Utilities . Last...

Matter

New Transmission Line

Represented a wind developer on the environmental and land use permits for a 15-mile, 115 kV transmission line connecting the Northern Maine transmission system to ISO-New England.

Blog

Maine’s COVID-19 Response Impacts Utility Services and Other Business Activities

Like many states, Maine is quickly imposing a wide range of measures designed to protect the public in response to the spread of the coronavirus, COVID-19. Almost daily, Maine Governor Janet Mills and other...