Maine PUC Clarifies Ability of Level 2 Projects to “Leapfrog” Level 4 Projects in Interconnection Queue

November 2, 2022 Alerts and Newsletters

After months of uncertainty over the issue of whether Level 2 renewable energy projects can “leapfrog” Level 4 projects in the queue, the Maine PUC clarified one of the ambiguities.

Specifically, in response to a petition we filed over the summer on behalf of a renewable energy developer, the Maine PUC issued an order at the end of October clarifying that developers may pay 100% of their known interconnection costs prior to completion of cluster studies that determine their transmission costs and be considered “aggregated generation” under Chapter 324. This is an important development that should reduce the frequency of Level 2 projects “leapfrogging” previously queued Level 4 projects that are stuck in cluster studies.

This issue arose in part due to a waiver granted by the PUC to CMP in September 2020 regarding Sections 12(S) and 12(T) of Chapter 324 of the Commission’s rules. This waiver allowed CMP to delay issuing construction schedules to customers in the interconnection queue until after the completion of the ISO-NE I.3.9 process. Pursuant to this waiver, T&D utilities adopted a policy of not invoicing Level 4 projects for payments of the estimated costs of interconnection upgrades until after the I.3.9 determination and cost allocations from ISO-NE cluster studies were complete.

This waiver had little adverse impact on a Level 4 Project until January 2022 when the MPUC amended Chapter 324 and adopted a definition of Aggregated Generation that excluded projects that had not paid 100% of estimated interconnection costs. Specifically, only the following are considered Aggregated Generation under the new definition: the project proposed by the applicant, in-service projects, and “all ICGFs that have paid the T&D Utility for 100% of interconnection-related costs attributable to it, including costs for studies, distribution facilities, systems upgrades, metering, and other items [for] which the ICGF has cost responsibility.” Previously, the utilities had treated all queued generation as aggregated generation. As a result of this new definition, Level 4 projects that have not paid 100% of their interconnection costs were no longer considered aggregated generation.

The combination of the definition of Aggregated Generation and the waiver that permitted delayed invoicing caused havoc in the queue. Level 2 projects were able to leapfrog Level 4 projects because the Level 4 projects were not considered when the utility applied the screening criteria to determine whether there was adequate capacity in the system to accommodate the proposed Level 2 project. When Level 4 projects asked to be invoiced so that they would be treated as aggregated generation, the T&D utilities pointed to the waiver and indicated that the invoices could not be issued until the cluster studies were completed and I.3.9 approval obtained. Each time a Level 2 project leapfroggs the queue, it forces a sequential restudy of all Level 4 projects in the queue. This results in significant delays to accommodate the required restudies, potential increases in interconnection costs resulting from such restudies, and undermines the commercial viability of projects that may otherwise have been shovel ready.

Verrill has filed several petitions seeking relief from the adverse consequences of the new definition of Aggregated Generation and the impact of Level 2 projects leapfrogging previously queued Level 4 projects. The MPUC issued the attached Order that provides partial relief and that allows projects to pay 100% of known interconnection costs prior completion of cluster studies and I.3.9 approval. The Commission points out that by allowing projects to pay 100% of their known interconnection costs, the utility will be able to consider the generation from these projects when screening future Level 2 projects. Although it does not solve the problem entirely, it provides partial relief from the draconian impact of the definition of Aggregated Generation.

For further information please contact Juliet Browne or Jonathan M. Dunitz.

Firm Highlights

Publication/Podcast

Maine Legislature Poised to Make Significant Changes to Maine’s PFAS in Products Law

Verrill’s Mat Todaro and Maye Emlein recently authored an article for Law360 regarding proposed changes to Maine’s PFAS in Products Law. To read the article in its entirety, please click here .

News

Verrill Recognized Nationally for Health Care, Land Use and Zoning, Commercial Litigation, Real Estate, and Trust & Estates by Best Lawyers®

Blog

U.S. Environmental Protection Agency Proposes National Drinking Water Standard for Six PFAS Compounds

On March 14, 2023, the U.S. Environmental Protection Agency (“EPA”) announced a proposed National Primary Drinking Water Regulation (NPDWR) for six per- and polyfluoroalkyl substances (“PFAS”). PFAS are a category of manufactured chemicals that...

Blog

Carolyn Gilbert Nominated to Maine PUC

On March 28, Governor Janet Mills nominated Carolyn “Carrie” Gilbert to serve a six-year term on the Maine Public Utilities Commission. For the past 15 years, Gilbert has worked at Daymark Energy Advisors where...

Blog

Maine Voters Reject “Pine Tree Power” Proposal

Last Tuesday, by a margin of 70% to 30%, Maine voters rejected Question 3, the highest profile issue on the Maine ballot this year. Question 3 was placed on the ballot earlier this year...

Blog

PFAS Regulatory Update: Dates You Need to Know

Public Comment on the Federal Proposed Drinking Water Standards for Six PFAS Compounds On March 29, 2023, the U.S. Environmental Protection Agency (“EPA”), published in the Federal Register its proposed national drinking water standards...

News

82 Verrill Attorneys Recognized by Best Lawyers® 2024, Including 10 Named Lawyers of the Year

News

Verrill Attorney Jonathan Dunitz Appointed Member of the State of Maine Supreme Judicial Court’s Access to Justice Tax Credit Committee

Blog

Verrill Partner Jim Cohen Speaks to Groups Across Maine About Pine Tree Power

For nearly two years, Verrill partner Jim Cohen , who has been practicing energy and utilities law for more than three decades, has been traveling throughout the State of Maine to speak with numerous...

Blog

Maine PUC Amends Small Generator Interconnection Procedures Rules (Chapter 324)

On November 3, 2023, the Maine Public Utilities Commission (the “Commission”) issued an Order adopting amendments to its Small Generator Interconnection Procedures Rule (Chapter 324). Background. Chapter 324 was last amended on December 21...

Contact Verrill at (855) 307 0700