Environmental and Energy Law Update
        A blog from the attorneys of Verrill

        Maine PUC Asked to Fix “Leapfrogging” Problem Triggered by 2022 Changes to Maine’s Generator Interconnection Rule

        by James I. Cohen on March 2, 2023

        The Maine Public Utilities Commission is currently considering whether to commence a formal emergency rulemaking process to amend Chapter 324 of its rules governing generator interconnections. The purpose of the rulemaking would be to correct a growing problem whereby smaller “Level 2” interconnection projects are able to “leapfrog” larger “Level 4” projects in the interconnection queue, triggering restudies and delays for Level 4 projects that have completed their distribution level interconnection studies but are awaiting final I.3.9 approval.

        The emergency rulemaking was initially requested through a joint petition filed in December by Central Maine Power Company, Versant Power Company, Maine Renewable Energy Association, and the Coalition for Community Solar Access. A link to the Petition, which is part of Docket No. 2022-00359.

        More specifically, Petitioners seek to resolve the “leapfrogging” issue that Level 4 projects have faced since the Commission’s 2022 adoption of a new definition of “Aggregated Generation” in Chapter 324. Under the new definition, a Level 4 project is not considered “aggregated generation” with a fixed spot in the interconnection queue until it has entered into an interconnection agreement with the utility AND paid for all required interconnection upgrades. Many Level 4 projects wanted to pay 100% of the interconnection costs, but were not able to do so due because delays in the cluster study results made it impossible to determine the interconnection costs.

        Since the adoption of the new definition of “aggregated generation” in Ch. 324, CMP and Versant say they have seen a significant increase in Level 2 interconnection requests, and each Level 2 request that “leapfrogs” a Level 4 request awaiting the results of an I.3.9 Cluster Study forces a restudy of the Level 4 project. In practice, there is no limit to the number of Level 2 projects can apply for interconnection and force the Level 4 project to undergo restudies. The longer the delay in the I.3.9 process, the greater the likelihood that a Level 4 project will confront one or more of these “leapfrog” situations.

        To address the leapfrogging issue, the Commission issued an advisory ruling clarifying that Level 4 projects that have paid 100% of distribution costs (but not transmission costs) may be considered “Aggregated Generation.” Central Maine Power Company, Request for Approval Waiver of Chapter 324, Docket No. 2020- 00211, Order Clarifying Order Granting Waiver, at 1-2 (Oct. 20, 2022). In this ruling, the Commission further clarified the timing and process for Level 4 projects requesting an invoice for 100% of distribution costs while awaiting the results of a Section I.3.9 cluster study by noting that projects should be allowed to pay 100% of known distribution costs prior to I.3.9 approval if the project developer is willing to do so. Id.

        The proposed emergency rule amendments sought in this proceeding include:

        1. Formally codifying in Chapter 324 the terms of the advisory ruling issued by the Commission in Central Maine Power Company, Request for Approval Waiver of Chapter 324, Docket No. 2020-00211, Order Clarifying Order Granting Waiver, at 1-2 (Oct. 20, 2022);
        2. Reducing the maximum size of a Level 2 project from 2 MW to 1 MW; and
        3. Introducing a site control requirement on certain Level 2 interconnection requests to reduce the number of speculative Level 2 requests.

        Following the submission of the emergency rulemaking petition, the Commission sought comments on eleven different issues relating to the appropriateness of emergency rulemaking. The Petitioners submitted comments in response to the Commission’s Request, and the Office of Public Advocate also submitted comments citing no objection to the proposed revisions to Chapter 324. However, OPA questioned the “emergency” nature of the rulemaking request, including its view that the Petitioners had failed to demonstrate that, absent the rulemaking, there would be an immediate threat to public health, safety, or the general welfare.

        On February 3, 2023, the Commission issued a Procedural Order seeking further clarification from the Petitioners regarding:

        1. Data supporting the analysis performed by CMP and Versant in calculating the number of Level 2 projects each utility has in their queue; and
        2. The relationship between the projects included in the publicly available Level 2 Application Tracker on the CMP website and the number of Level 2 projects received by CMP and Versant.

        On February 13, 2023, CMP and Versant each filed responses and data sets in accordance with the Commission’s request for clarification.

        At this stage, the Commission will consider all of the information filed to date and either issue further information requests or proceed to rule on the request for emergency rulemaking.

        As always, if you have any questions or want further information, please do not hesitate to contact one of our Energy, Telecommunications & Natural Resources attorneys.

        Environmental and Energy Law Update

        The Environmental and Energy Law Update blog provides an analysis and discussion of the most critical and timely legal issues and announcements in the environmental, natural resource, and energy sectors.

        Subscribe

        Looking for more great content? Subscribe for regular legal updates and information delivered right to your inbox.

        Firm Highlights

        Blog

        Maine’s Noncompete Statute is Reshaped for Health Care Workers: What You Need to Know

        Employers of individuals who are licensed under state law to perform, or provide, health care services in the State of Maine should be prepared for...
        Media Mentions

        Steven Davis Featured in the Environmental Business Journal

        Steven Davis, President of Verrill Strategic Consulting, was recently interviewed and featured in the Environmental Business Journal, Volume 39...
        Blog

        What is a Bonus for Purposes of ERISA?

        An ongoing dispute about a Department of Labor advisory opinion published last September raises a basic but unanswered question under the ERISA: What...
        Media Mentions

        Verrill Recognized by WMTW for Partnership Supporting Hunger Relief in Maine

        Verrill was recently featured in coverage by WMTW News 8 for its role in a collaborative effort to combat food insecurity across southern...
        Press Releases

        33 Verrill Attorneys, Across Four Offices, Recognized in the 2026 Chambers USA Guide

        BOSTON, Massachusetts, PORTLAND, Maine, WESTPORT, Connecticut, and WASHINGTON, D.C. – Verrill has been recognized as a Leading Firm in 14...
        Blog

        Will the Knicks Beat the Spurs? (Are Prediction Market Event Contracts Gambling?)

        For those of you who like to keep score, currently 18 states are engaged in litigation over prediction markets, such as Kalshi and Polymarket,...
        Alerts and Newsletters

        DOJ Announces Faster Review and Enhanced Enforcement for Benefits-Fraud FCA Matters

        On May 27, 2026, the U.S. Department of Justice (DOJ) Civil Division issued a new memorandum, “Accelerating Review and Enhancing Enforcement in...
        Alerts and Newsletters

        DOJ Announces Minnesota Health Care Fraud Takedown; Signals Intensified Medicaid Enforcement Nationwide

        On May 21, the Department of Justice (“DOJ”) announced a first-of-its kind Minnesota Health Care Fraud Takedown charging 15 defendants, including...
        Media Mentions

        Lauren Galvin Quoted in Massachusetts Lawyers Weekly on Arbitration and Anti-SLAPP Protections

        Verrill Partner Lauren Galvin was recently featured in a Massachusetts Lawyers Weekly article highlighting a notable Superior Court decision...
        Blog

        Section 530A Accounts: What Employers Should Consider Before Offering Contributions to “Trump” Accounts

        Section 530A accounts, commonly referred to as Trump accounts, have attracted attention since the enactment of the One Big Beautiful Bill Act in...
        Blog

        Navigating PBM Reform: Regulatory Changes, Market Shifts, and Practical Guidance for ERISA Fiduciaries

        Pharmacy Benefit Manager (“PBM”) arrangements have long relied on rebates with limited transparency into true drug costs. Recent regulatory and...
        Blog

        DOL’s Proposed Regulation on Selecting Alternative Investments: Broad Implications for 401(k) and 403(b) Plan Fiduciaries

        On March 30, 2026, the Department of Labor issued a proposed regulation purporting to implement an executive order to expand access to “alternative...