Environmental and Energy Law Update
        A blog from the attorneys of Verrill

        Maine PUC Asked to Fix “Leapfrogging” Problem Triggered by 2022 Changes to Maine’s Generator Interconnection Rule

        by James I. Cohen on March 2, 2023

        The Maine Public Utilities Commission is currently considering whether to commence a formal emergency rulemaking process to amend Chapter 324 of its rules governing generator interconnections. The purpose of the rulemaking would be to correct a growing problem whereby smaller “Level 2” interconnection projects are able to “leapfrog” larger “Level 4” projects in the interconnection queue, triggering restudies and delays for Level 4 projects that have completed their distribution level interconnection studies but are awaiting final I.3.9 approval.

        The emergency rulemaking was initially requested through a joint petition filed in December by Central Maine Power Company, Versant Power Company, Maine Renewable Energy Association, and the Coalition for Community Solar Access. A link to the Petition, which is part of Docket No. 2022-00359.

        More specifically, Petitioners seek to resolve the “leapfrogging” issue that Level 4 projects have faced since the Commission’s 2022 adoption of a new definition of “Aggregated Generation” in Chapter 324. Under the new definition, a Level 4 project is not considered “aggregated generation” with a fixed spot in the interconnection queue until it has entered into an interconnection agreement with the utility AND paid for all required interconnection upgrades. Many Level 4 projects wanted to pay 100% of the interconnection costs, but were not able to do so due because delays in the cluster study results made it impossible to determine the interconnection costs.

        Since the adoption of the new definition of “aggregated generation” in Ch. 324, CMP and Versant say they have seen a significant increase in Level 2 interconnection requests, and each Level 2 request that “leapfrogs” a Level 4 request awaiting the results of an I.3.9 Cluster Study forces a restudy of the Level 4 project. In practice, there is no limit to the number of Level 2 projects can apply for interconnection and force the Level 4 project to undergo restudies. The longer the delay in the I.3.9 process, the greater the likelihood that a Level 4 project will confront one or more of these “leapfrog” situations.

        To address the leapfrogging issue, the Commission issued an advisory ruling clarifying that Level 4 projects that have paid 100% of distribution costs (but not transmission costs) may be considered “Aggregated Generation.” Central Maine Power Company, Request for Approval Waiver of Chapter 324, Docket No. 2020- 00211, Order Clarifying Order Granting Waiver, at 1-2 (Oct. 20, 2022). In this ruling, the Commission further clarified the timing and process for Level 4 projects requesting an invoice for 100% of distribution costs while awaiting the results of a Section I.3.9 cluster study by noting that projects should be allowed to pay 100% of known distribution costs prior to I.3.9 approval if the project developer is willing to do so. Id.

        The proposed emergency rule amendments sought in this proceeding include:

        1. Formally codifying in Chapter 324 the terms of the advisory ruling issued by the Commission in Central Maine Power Company, Request for Approval Waiver of Chapter 324, Docket No. 2020-00211, Order Clarifying Order Granting Waiver, at 1-2 (Oct. 20, 2022);
        2. Reducing the maximum size of a Level 2 project from 2 MW to 1 MW; and
        3. Introducing a site control requirement on certain Level 2 interconnection requests to reduce the number of speculative Level 2 requests.

        Following the submission of the emergency rulemaking petition, the Commission sought comments on eleven different issues relating to the appropriateness of emergency rulemaking. The Petitioners submitted comments in response to the Commission’s Request, and the Office of Public Advocate also submitted comments citing no objection to the proposed revisions to Chapter 324. However, OPA questioned the “emergency” nature of the rulemaking request, including its view that the Petitioners had failed to demonstrate that, absent the rulemaking, there would be an immediate threat to public health, safety, or the general welfare.

        On February 3, 2023, the Commission issued a Procedural Order seeking further clarification from the Petitioners regarding:

        1. Data supporting the analysis performed by CMP and Versant in calculating the number of Level 2 projects each utility has in their queue; and
        2. The relationship between the projects included in the publicly available Level 2 Application Tracker on the CMP website and the number of Level 2 projects received by CMP and Versant.

        On February 13, 2023, CMP and Versant each filed responses and data sets in accordance with the Commission’s request for clarification.

        At this stage, the Commission will consider all of the information filed to date and either issue further information requests or proceed to rule on the request for emergency rulemaking.

        As always, if you have any questions or want further information, please do not hesitate to contact one of our Energy, Telecommunications & Natural Resources attorneys.

        Environmental and Energy Law Update

        The Environmental and Energy Law Update blog provides an analysis and discussion of the most critical and timely legal issues and announcements in the environmental, natural resource, and energy sectors.

        Subscribe

        Looking for more great content? Subscribe for regular legal updates and information delivered right to your inbox.

        Firm Highlights

        Media Mentions

        Martha Gaythwaite Featured in Portland Press Herald Coverage of Sig Sauer Trial Victory

        Verrill attorney Martha Gaythwaite was highlighted in media coverage of a federal trial in Bangor involving firearm manufacturer Sig Sauer. As...
        Alerts and Newsletters

        SAFEs and Preferred Stock – Key Deal Terms Every Founder Should Know

        SAFEs Before negotiating a term sheet for preferred stock, many early-stage companies, particularly at the seed stage, first raise capital through...
        Press Releases

        Verrill Welcomes Business Restructuring and Insolvency Attorney Nimra Tariq

        BOSTON, Massachusetts – Verrill is pleased to announce that Nimra Tariq has joined the firm’s Business Restructuring and Insolvency Group as an...
        Media Mentions

        Robert Keach Quoted in Law360 on First Brands Chapter 11 Plan

        Verrill attorney Robert Keach was quoted in the Law360 article,"First Brands' Ch. 11 Plan Revives Angst Over Admin Claims," discussing First Brands...
        Press Releases

        Verrill Welcomes Construction Attorney Cassie Dufon

        PORTLAND, Maine – Verrill is pleased to welcome Cassie Dufon to the firm’s Construction Group as an Associate, resident in the firm’s Portland...
        Press Releases

        Verrill’s Wide-Ranging Private Wealth Law Practice Recognized in 2026 Chambers and Partners High Net Worth Guide

        BANGOR and PORTLAND, Maine and BOSTON, Mass. – Verrill attorneys Kenneth P. Brier, Anya F. Endsley, Kurt E. Klebe, Mary McQuillen, Nathaniel S....
        Blog

        Update on Status of Maine Packaging EPR

        In December 2024, Verrill published a blog post, Unwrapping Maine's Gift to the Environment: A New Packaging Stewardship Program Set to Launch in...
        Blog

        Voluntary Benefits Move into the ERISA Litigation Crosshairs

        Employee-paid accident, critical-illness, cancer, and hospital-indemnity insurance have long occupied a quiet corner of employee benefit plan...
        Alerts and Newsletters

        Maine’s New Employer Surveillance Law, 26 M.R.S. § 620-A

        Effective July 14, 2026 Maine employers that electronically monitor employees must comply with a new disclosure law effective July 14, 2026. Under...
        Press Releases

        Verrill Recognized by U.S. News as One of the Best Law Firms to Work for in 2026

        BOSTON, Mass., BANGOR and PORTLAND, Maine, GREENWICH and WESTPORT, Conn., – Verrill has been featured on U.S. News’ 2026 Best Companies to Work...
        Blog

        SECURE 2.0 Roth Catch-Up Rules and the 403(b) 15-Year Catch-Up: What Tax-Exempt Employers Need to Know

        Tax-exempt employers whose 403(b) plans offer catch-up contributions for participants age 50 and above should be well on their way to compliance with...
        Media Mentions

        Robert Keach Quoted in Law360 on SIMAD Summer Camp Bankruptcy Sale

        Verrill attorney Robert Keach was recently quoted in a Law360 article examining the Chapter 11 bankruptcy proceedings involving SIMAD Holdings and...