Environmental and Energy Law Update
        A blog from the attorneys of Verrill

        Maine PUC Asked to Fix “Leapfrogging” Problem Triggered by 2022 Changes to Maine’s Generator Interconnection Rule

        by James I. Cohen on March 2, 2023

        The Maine Public Utilities Commission is currently considering whether to commence a formal emergency rulemaking process to amend Chapter 324 of its rules governing generator interconnections. The purpose of the rulemaking would be to correct a growing problem whereby smaller “Level 2” interconnection projects are able to “leapfrog” larger “Level 4” projects in the interconnection queue, triggering restudies and delays for Level 4 projects that have completed their distribution level interconnection studies but are awaiting final I.3.9 approval.

        The emergency rulemaking was initially requested through a joint petition filed in December by Central Maine Power Company, Versant Power Company, Maine Renewable Energy Association, and the Coalition for Community Solar Access. A link to the Petition, which is part of Docket No. 2022-00359.

        More specifically, Petitioners seek to resolve the “leapfrogging” issue that Level 4 projects have faced since the Commission’s 2022 adoption of a new definition of “Aggregated Generation” in Chapter 324. Under the new definition, a Level 4 project is not considered “aggregated generation” with a fixed spot in the interconnection queue until it has entered into an interconnection agreement with the utility AND paid for all required interconnection upgrades. Many Level 4 projects wanted to pay 100% of the interconnection costs, but were not able to do so due because delays in the cluster study results made it impossible to determine the interconnection costs.

        Since the adoption of the new definition of “aggregated generation” in Ch. 324, CMP and Versant say they have seen a significant increase in Level 2 interconnection requests, and each Level 2 request that “leapfrogs” a Level 4 request awaiting the results of an I.3.9 Cluster Study forces a restudy of the Level 4 project. In practice, there is no limit to the number of Level 2 projects can apply for interconnection and force the Level 4 project to undergo restudies. The longer the delay in the I.3.9 process, the greater the likelihood that a Level 4 project will confront one or more of these “leapfrog” situations.

        To address the leapfrogging issue, the Commission issued an advisory ruling clarifying that Level 4 projects that have paid 100% of distribution costs (but not transmission costs) may be considered “Aggregated Generation.” Central Maine Power Company, Request for Approval Waiver of Chapter 324, Docket No. 2020- 00211, Order Clarifying Order Granting Waiver, at 1-2 (Oct. 20, 2022). In this ruling, the Commission further clarified the timing and process for Level 4 projects requesting an invoice for 100% of distribution costs while awaiting the results of a Section I.3.9 cluster study by noting that projects should be allowed to pay 100% of known distribution costs prior to I.3.9 approval if the project developer is willing to do so. Id.

        The proposed emergency rule amendments sought in this proceeding include:

        1. Formally codifying in Chapter 324 the terms of the advisory ruling issued by the Commission in Central Maine Power Company, Request for Approval Waiver of Chapter 324, Docket No. 2020-00211, Order Clarifying Order Granting Waiver, at 1-2 (Oct. 20, 2022);
        2. Reducing the maximum size of a Level 2 project from 2 MW to 1 MW; and
        3. Introducing a site control requirement on certain Level 2 interconnection requests to reduce the number of speculative Level 2 requests.

        Following the submission of the emergency rulemaking petition, the Commission sought comments on eleven different issues relating to the appropriateness of emergency rulemaking. The Petitioners submitted comments in response to the Commission’s Request, and the Office of Public Advocate also submitted comments citing no objection to the proposed revisions to Chapter 324. However, OPA questioned the “emergency” nature of the rulemaking request, including its view that the Petitioners had failed to demonstrate that, absent the rulemaking, there would be an immediate threat to public health, safety, or the general welfare.

        On February 3, 2023, the Commission issued a Procedural Order seeking further clarification from the Petitioners regarding:

        1. Data supporting the analysis performed by CMP and Versant in calculating the number of Level 2 projects each utility has in their queue; and
        2. The relationship between the projects included in the publicly available Level 2 Application Tracker on the CMP website and the number of Level 2 projects received by CMP and Versant.

        On February 13, 2023, CMP and Versant each filed responses and data sets in accordance with the Commission’s request for clarification.

        At this stage, the Commission will consider all of the information filed to date and either issue further information requests or proceed to rule on the request for emergency rulemaking.

        As always, if you have any questions or want further information, please do not hesitate to contact one of our Energy, Telecommunications & Natural Resources attorneys.

        Environmental and Energy Law Update

        The Environmental and Energy Law Update blog provides an analysis and discussion of the most critical and timely legal issues and announcements in the environmental, natural resource, and energy sectors.

        Subscribe

        Looking for more great content? Subscribe for regular legal updates and information delivered right to your inbox.

        Firm Highlights

        Blog

        Hurry Up and Wait

        This is the third in a series of Verrill blog posts on Maine’s packaging extended producer responsibility (“EPR”) law[1]. In July we reported...
        Media Mentions

        Robert Keach Discusses First Brands Chapter 11 Case in Law360

        Verrill attorney Robert Keach was recently quoted in a Law360 article examining the rejection of First Brands Group's Chapter 11 plan and the...
        Media Mentions

        Cybersecurity and AI Governance: Scott Anderson Featured in Massachusetts Lawyers Weekly

        Verrill Managing Partner Scott Anderson was recently featured in Massachusetts Lawyers Weekly discussing how law firms can build attorney buy-in for...
        Blog

        Section 530A Account Update: ERISA Status of Trump Accounts

        The Department of Labor has issued important guidance addressing whether employer programs that permit contributions to Section 530A accounts (and...
        Press Releases

        97 Verrill Attorneys Recognized by Best Lawyers® 2027, Including Four Named Lawyers of the Year

        AUGUSTA, Maine, BANGOR, Maine, BOSTON, Mass., PORTLAND, Maine, and WESTPORT, Conn., (August 20, 2026) – Verrill is proud to announce that 97...
        Alerts and Newsletters

        SEC’s Proposed “Reg Crypto”: What Founders Need to Know

        Startup founders and emerging-growth companies have a number of options for raising capital under the federal securities laws, including Regulation D...
        Blog

        After 45 Years, the IRS Speaks on DCAP Nondiscrimination Testing – And It’s Good News

        Employers that provide a Dependent Care Assistance Program will be pleased to learn that for the first time in 45 years, the IRS has issued guidance...
        Media Mentions

        U.S. Courts Highlights Annabel Rodriguez’s Journey from Fellow to Mentor

        Verrill attorney Annabel Rodriguez was featured in a recent U.S. Courts article titled “From Fellows to Mentors: Alumni Share Lasting Lessons from...
        Media Mentions

        Robert Keach Discusses Bankruptcy Auction Strategy in Law360

        Verrill attorney Robert Keach spoke with Law360 article examining the complex bankruptcy auction process that resulted in the sale of 23 summer...
        Media Mentions

        Martha Gaythwaite Featured in Portland Press Herald Coverage of Sig Sauer Trial Victory

        Verrill attorney Martha Gaythwaite was highlighted in media coverage of a federal trial in Bangor involving firearm manufacturer Sig Sauer. As...
        Media Mentions

        Law360 Quotes Robert Keach on Senate Bill Affecting Small Business Restructurings

        Verrill attorney Robert Keach was recently quoted in a Law360 article discussing federal legislation that would permanently restore the $7.5 million...
        Alerts and Newsletters

        SAFEs and Preferred Stock – Key Deal Terms Every Founder Should Know

        SAFEs Before negotiating a term sheet for preferred stock, many early-stage companies, particularly at the seed stage, first raise capital through...